Patient transport lounge

Patient transport lounge

This project was split over 5 phases

  • Starting with the demolitions of existing offices to open up for the new PTL, reception and bed bay

  • Following the handover of the area we then started on the 10 consulting rooms that included new medical trunking, clinical sinks and surface finishes

  • The final 2 phases were done on live day wards and toilet facilities. These works had to be very carefully co-ordinated alongside the staff to ensure minimal disruption was caused.

  • This project was handed over on time and on budget.